Certified Scrum Product Owner (CSPO) Practice Exam 2025 - Free Scrum Product Owner Practice Questions and Study Guide

Question: 1 / 400

How is the work to be accomplished during a Sprint presented in Scrum?

In a detailed project plan

As a Gantt chart

In the Sprint Backlog

The work to be accomplished during a Sprint in Scrum is presented in the Sprint Backlog. The Sprint Backlog is a dynamic list that contains all the tasks and items selected from the Product Backlog for the Sprint, along with a plan for delivering the Increment of the product. It provides clarity on what the team aims to achieve during the Sprint and acts as a guide for the team’s daily work.

The Sprint Backlog is essential because it reflects the team’s commitment to completing specific work within the Sprint time frame, allowing team members to collaboratively understand their priorities and focus. It is a living artifact that can be updated as the team progresses through the Sprint, ensuring transparency and adaptability.

While other methods, such as detailed project plans or Gantt charts, may provide a broader overview of project timelines and activities, they do not align with the agile principles of Scrum, which emphasize flexibility, iterative progress, and adaptability. The retrospective document, on the other hand, is a record of the team's reflections on the past Sprint and does not serve as a means to plan the current Sprint's work. Thus, the Sprint Backlog uniquely fulfills the requirement to present and manage the tasks of each Sprint effectively.

Get further explanation with Examzify DeepDiveBeta

As part of the retrospective document

Next Question

Report this question

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy